Update - 29 April 2024

Trial hole excavation works to begin

We are starting trial hole excavation works in a number of locations to help us finalise the design for the Connecting Sheffield: Nether Edge – city centre project.

Works start on Wednesday 1 May, and will help us to confirm where different services are located underground.

We will use a very large vacuum excavator, which will create some noise, but we aim to complete each trial hole and reinstate the paving within a day. But there may be some instances where this may take an extra day.

Due to the location of some of the holes we need to excavate, we will need to do some of the works overnight. We will aim to complete these as quickly as possible and will aim to minimise disruption as far as possible.

The table below shows when and where we will be doing the trial hole work, and whether the work will be at night.

Trial hole Work duration Start Finish Working hours Location
Trial hole 3 1 day Wednesday 1 May Wednesday 1 May 9.30am to 3.30pm Wostenholm Road
Trial hole 4 1 day Thursday 2 May Thursday 2 May 9.30am to 3.30pm Sharrow Lane
Trial hole 5 1 day Friday 3 May Friday 3 May 9.30am to 3.30pm Washington Road
Trial hole 21 1 day Sunday 5 May Sunday 5 May 8am to 5pm Summerfield Street
Trial hole 6 1 day Tuesday 7 May Tuesday 7 May 9.30am to 3.30pm Washington Road
Trial hole 8 1 day Wednesday 8 May Wednesday 8 May 9.30am to 3.30pm Washington Road
Trial hole 11 1 day Thursday 9 May Thursday 9 May 9.30am to 3.30pm Cemetery Road
Trial hole 13 1 day Friday 10 May Friday 10 May 9.30am to 3.30pm Cemetery Road
Trial hole 23 1 day Sunday 12 May Sunday 12 May 8am to 5pm Summerfield Street
Trial hole 22 1 day Monday 13 May Monday 13 May 9.30am to 3.30pm Napier Street
Trial Hole 37 (shown as 37B on plan)
1 day Tuesday 14 May Tuesday 14 May 7.30am to 5pm Napier Street
Trial Hole 36
1 day Wednesday 15 May Wednesday 15 May 7.30am to 5pm Washington Road
Trial Hole 38 (shown as 37A on plan)
1 day Thursday 16 May Thursday 16 May 9.30am to 3.30pm Cemetery Road
Trial Hole 16
1 day Friday 17 May Friday 17 May 9.30am to 3.30pm Cemetery Road
Trial Hole 20
1 day Sunday 19 May Sunday 19 May 8am to 5pm Cemetery Road
Trial Hole 17
1 day Monday 20 May Monday 20 May 7.30am to 5pm Cemetery Road
Trial Hole 19
1 day Tuesday 21 May Tuesday 21 May 7.30am to 5pm Cemetery Road
Trial Hole 39
1 day Wednesday 22 May Wednesday 22 May Overnight - 8pm to 5am Moore Street
Trial Hole 33
1 day Thursday 23 May Thursday 23 May Overnight - 8pm to 5am Moore Street
Trial Hole 32
1 day Tuesday 28 May Tuesday 28 May Overnight - 8pm to 5am Moore Street
Trial Hole 34
1 day Wednesday 29 May Wednesday 29 May Overnight - 8pm to 5am Charter Row
Trial hole 35 1 day Thursday 30 May Thursday 30 May Overnight - 8pm to 5am Trafalgar Street


You can view PDF plans of where the trial holes are located below:

Charter Row

Charter Row and Moore Street

South Lane and St Mary's Gate

Summerfield Street, Napier Street, Cemetery Road and Washington Road

Washington Road and Sharrow Lane

Wostenholm Road and Sharrow Lane

If you have any questions about the trial hole works, you can email us via transport@sheffield.gov.uk

We'll update you on the wider project proposals in the coming months, when we've finalised the designs.

Share Update - 29 April 2024 on Facebook Share Update - 29 April 2024 on Twitter Share Update - 29 April 2024 on Linkedin Email Update - 29 April 2024 link
#<Object:0x000000000fbda128>