Update - 29 April 2024
Trial hole excavation works to begin
We are starting trial hole excavation works in a number of locations to help us finalise the design for the Connecting Sheffield: Nether Edge – city centre project.
Works start on Wednesday 1 May, and will help us to confirm where different services are located underground.
We will use a very large vacuum excavator, which will create some noise, but we aim to complete each trial hole and reinstate the paving within a day. But there may be some instances where this may take an extra day.
Due to the location of some of the holes we need to excavate, we will need to do some of the works overnight. We will aim to complete these as quickly as possible and will aim to minimise disruption as far as possible.
The table below shows when and where we will be doing the trial hole work, and whether the work will be at night.
Trial hole | Work duration | Start | Finish | Working hours | Location |
---|---|---|---|---|---|
Trial hole 3 | 1 day | Wednesday 1 May | Wednesday 1 May | 9.30am to 3.30pm | Wostenholm Road |
Trial hole 4 | 1 day | Thursday 2 May | Thursday 2 May | 9.30am to 3.30pm | Sharrow Lane |
Trial hole 5 | 1 day | Friday 3 May | Friday 3 May | 9.30am to 3.30pm | Washington Road |
Trial hole 21 | 1 day | Sunday 5 May | Sunday 5 May | 8am to 5pm | Summerfield Street |
Trial hole 6 | 1 day | Tuesday 7 May | Tuesday 7 May | 9.30am to 3.30pm | Washington Road |
Trial hole 8 | 1 day | Wednesday 8 May | Wednesday 8 May | 9.30am to 3.30pm | Washington Road |
Trial hole 11 | 1 day | Thursday 9 May | Thursday 9 May | 9.30am to 3.30pm | Cemetery Road |
Trial hole 13 | 1 day | Friday 10 May | Friday 10 May | 9.30am to 3.30pm | Cemetery Road |
Trial hole 23 | 1 day | Sunday 12 May | Sunday 12 May | 8am to 5pm | Summerfield Street |
Trial hole 22 | 1 day | Monday 13 May | Monday 13 May | 9.30am to 3.30pm | Napier Street |
Trial Hole 37 (shown as 37B on plan) |
1 day | Tuesday 14 May | Tuesday 14 May | 7.30am to 5pm | Napier Street |
Trial Hole 36 |
1 day | Wednesday 15 May | Wednesday 15 May | 7.30am to 5pm | Washington Road |
Trial Hole 38 (shown as 37A on plan) |
1 day | Thursday 16 May | Thursday 16 May | 9.30am to 3.30pm | Cemetery Road |
Trial Hole 16 |
1 day | Friday 17 May | Friday 17 May | 9.30am to 3.30pm | Cemetery Road |
Trial Hole 20 |
1 day | Sunday 19 May | Sunday 19 May | 8am to 5pm | Cemetery Road |
Trial Hole 17 |
1 day | Monday 20 May | Monday 20 May | 7.30am to 5pm | Cemetery Road |
Trial Hole 19 |
1 day | Tuesday 21 May | Tuesday 21 May | 7.30am to 5pm | Cemetery Road |
Trial Hole 39 |
1 day | Wednesday 22 May | Wednesday 22 May | Overnight - 8pm to 5am | Moore Street |
Trial Hole 33 |
1 day | Thursday 23 May | Thursday 23 May | Overnight - 8pm to 5am | Moore Street |
Trial Hole 32 |
1 day | Tuesday 28 May | Tuesday 28 May | Overnight - 8pm to 5am | Moore Street |
Trial Hole 34 |
1 day | Wednesday 29 May | Wednesday 29 May | Overnight - 8pm to 5am | Charter Row |
Trial hole 35 | 1 day | Thursday 30 May | Thursday 30 May | Overnight - 8pm to 5am | Trafalgar Street |
You can view PDF plans of where the trial holes are located below:
Summerfield Street, Napier Street, Cemetery Road and Washington Road
Washington Road and Sharrow Lane
Wostenholm Road and Sharrow Lane
If you have any questions about the trial hole works, you can email us via transport@sheffield.gov.uk
We'll update you on the wider project proposals in the coming months, when we've finalised the designs.

Thank you for your contribution!