October 2024 - Psalter Lane permanent crossing

Construction programme for the permanent crossing

The main works to make the temporary crossing permanent will take place from 7 October to mid November. We will do most of the works between 9.30am to 4pm, Monday to Friday, although we may need to do some weekend working.

We’re hoping to finish all the works during the day, but depending on the weather we may need to do some night working. If this is the case, we will put some temporary signs in the area advising of any night working, if it's needed. We apologise in advance for any disturbance this may cause.

Managing disruption

We understand that the works will cause some disruption. To minimise this, we will do most of the works in off-peak times during the week, and we will put up temporary traffic lights to help vehicles pass the site in both directions. We will ensure the road is clear during busy periods such as the morning and evening commutes.

More information and getting in touch

If you have any questions or comments, you can contact us through the following channels:

You can see a layout plan of the new crossing below.


A plan of the new permanent zebra crossing to be installed On Psalter Lane by the junction of Osborne Road and Stretton RoadPlan of the permanent crossing layout on Psalter Lane

You can view this map as a pdf so you can zoom in.