May 2025

Outline Business Case (OBC)

The Outline Business Case submission will ask for approval to move forward with a detailed design for the playground and new MUGA surface

June 2025

Detailed design period

Through-out the detailed design period the Landscape Architect will ensure all elements of the design are considered within the budget available.  

October 2025

Tender period

The project will go out to tender.

03 November 2025

Tender evaluation

The tender will be cost assessed against the budget available. 

November 2025

Final Business Case (FBC) Submitted

The designs will now be finalised and cost agreed in the Final Business Case. 

December 2025

Order placed

An order will be placed with the chosen contractor and orders made for the play equipment.

March 2026

Work starts on site

The works will take approximately 12 weeks. 

June 2026

Playground improvements open

The playground/MUGA improvements will take approximately 12 weeks to complete.