May 2025

Outline Business Case (OBC)

The Outline Business Case submission will ask for approval to move forward with a detailed design for the playground and new MUGA surface

June 2025

Detailed design period

Through-out the detailed design period the Landscape Architect will ensure all elements of the design are considered within the budget available.  

August 2025

Tender period

The project will go out to tender.

01 September 2025

Tender evaluation

The tender will be cost assessed against the budget available. 

September 2025

Final Business Case (FBC) Submitted

The designs will now be finalised and cost agreed in the Final Business Case. 

October 2025

Order placed

An order will be placed with the chosen contractor and orders made for the play equipment.

January 2026

Work starts on site

Work will start on site.

April 2026

Playground improvements open

The playground/MUGA improvements will take approximately 12 weeks to complete.