Update - August 2024

Crookes permanent crossing

Construction programme and night working

The main kerbing works to make the temporary crossing permanent will be from 5 August 2024 to 30 August 2024. We will do most of the works between 9:30am-4pm, Monday to Friday, although we may need to do some weekend working.

We will need to do surfacing works during the night, from 9pm to 5am. We are anticipating these works will start in the week commencing 2 September 2024, taking up to 4 nights, but please be aware that this is weather dependant. Further information will be provided closer to this date.

Managing disruption

We understand that the works will cause some disruption. To minimise this, we will do most of the works in off-peak times during the week and will ensure the road is clear during busy periods such as the morning and evening commutes.

For the four nights we need to work, we will do all we can to reduce the impact on local residents. We apologise in advance for any disturbance this may cause.

Share Update - August 2024 on Facebook Share Update - August 2024 on Twitter Share Update - August 2024 on Linkedin Email Update - August 2024 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>